Deepening and normalisation Pun Hlaing River

Location: 
Myanmar
Year: 
2014
Description: 

Deepening and normalization of the Pun Hlaing River, Hlaing Thar Yar Township, in Myanmar.
The project was commissioned by the Irrigation department and last until May 2015.
The total length of the river segment to be dredged is 30 miles.
Dragflow provided one Hydraulic pump model HY85B plus cutters, flow rate divider system, and 130 m dredging hoses plus dredging pipes with its floaters.
The estimated production is 400 m3 per hour. The commissioning of the units was a huge success. Actual production is as planned.
The contractor is very pleased with this equipment.

Images: